NASR Consortium (Phase 12 South Pars)
Back to Top
Iinsallation & commissioning of electrical & mechanical equipment
Activity list of contract:
- conduit piping
- Metal work and supporting
- Cabling with armord cable( 2*2.5 -2*1.5)
- Scaffolding
- wiring
- Cabling withPVC cable -Low size
- Buldings outlet socket system installation-LCS
- lighting panel installation -ELP
- F&G panel installation
- UPS installation for emegency power system
- NLP system equipment installation
- earth cabling
- lighting pole and socket installation
- IT system equipment installation
- F&G system equipment installation
- Heating and coling fancoil installation
- PA/GA equipment installation
- Outdoor lighting
- lader and cable tray installation
- ducting for HVAC system
- Piping for HVAC hot and cold water
- fire fighting piping
- heat isolation for HVAC duct
|
Water research institute
Back to Top
procurement, installation, commissioning of rever over flow detecting system for Azar bayjan SEFID ROD
Activity list of contract:
- Introduction and equipment installation of 28weatherman station
- Introduction and equipment installation of 13 hydrometery station
- Introduction and equipment installation of 70 local alarm station
- Introduction and equipment installation of 2monitorin control center, procurement of rquired hard ware and software
|
O.I.E.C (RAMSHIR)
Back to Top
Installation and Pre commissioning of electrical and instrument of Phase 9&10
(South Pars Economic Energy Zone)
(Jan 2007 to Feb 2009)
This project includes all electrical and instrument works at Phase 9&10, area C.
Electrical works:
- Installation, test & oil treatment of 18 set power transformers.
- Installation, test & power on of 5 set dry transformers.
- Installation of 24 Cell MV panel, 349 feeder LV panel, 5 Cell UPS, 10 Cell NGR.
- Installation of 12 Rack Batteries.
- Installation of 293,000 meter Power and Control cables.
- Installation of 208 Pcs. LCS & Receptacles.
- Installation of 72 set HV termination.
- Installation of 5600 meter conduit.
- Installation of 31,000 meter Ladder & tray.
- Installation of 44,000 meter earth cables and accessories.
- Installation of 2211 Nos. fixtures and 49,000 meter lighting cables.
- Installation of 8300 meter cathodic cable, 16 Anode and 59 Nos. devices and other accessories.
- Installation of 6000 meter heat tracing cables.
- Installation of 36,000 meter fire alarm cables
- Fabrication and installation of 82,000 kg support for electrical part.
Instrument works:
- Installation of 74 Cell control panels in ITR.
- Installation of 225 Cell control panel for valves.
- Installation of 32,000 meter cable tray.
- Installation of 328,000 control cables.
- Installation of 414 Nos. junction boxes.
- Installation of 4600 meter air pipe and accessories.
- Calibration of 1005 set instrument devices.
- Fabrication and installation of 118,000 kg support for instrument part.
|
A.Z.A.A.N CONSORTIUM
Back to Top
Installation of electrical and instrument of Offsite Lines of Petrochemical Zone ( Mobin Petrochemical Company) , South Pars Special Economic Zone (Assaluye), and Installation, testing, alignment and pre-commissioning of fire water pump stations. (Apr 2005 to Feb 2008)
Electrical works:
- Installation of 243 Cell Panel (MV , LV , AVR , 132 KV Protection panel, UPS AC & DC, NGR , Wall mounted , Load shedding , Diesel control panel)
- Fabrication and installation of 18 ton Support, 1750 Meter ladder,3450 meter conduit.
- Installation of 398 Nos. Street lighting pole with 530 Nos. luminaries and installation of 5 pump station substation building lighting.
- Installation of 58 Km Earthing Cables (1*240, 1*120, 1*95, 1*25) and earth accessories For offsite Pipe racks, lighting routs and main earth ring.
- Installation of 83 Km Power, Control & lighting Cables and accessories.
- Installation of 52 Km Fiber Optic Cables (for 132 KV protection) and accessories.
- Installation of 8 Km cathodic protection cables, 140 Pcs. Anodes, 4 set transformer rectifier and negative, positive. & test bond boxes.
- Installation of 32 Km Fire alarm cables, 150 Pcs. Fire alarm detectors and other devices.
Instrument works:
- Installation of 93 Cell Panel (DCS , ESD , Network fiber optic and Patch panels)
- Fabrication and installation of 9 ton Support, 5200 Meter tray, 900 meter conduit.
- Installation of 59 Km instrument cables, fiber optic and earthing cables and accessories for control systems.
- Calibration and installation of 199 set instrument devices (flow , pressure , level transmitter and gauges)
Mechanical works:
- Installation and alignment of 30 set 6 KV pumps, Diesel and jockey pumps in 3 Fire pump station.
|
MEAM TEAM – ASFALT TOUS CONSORTIUM
Back to Top
Installation of Heavy Equipments, Furnaces and Pumps and Installation of Refractory of Incineration Petrochemical Zone ( Mobin Petrochemical Company) In South Pars Special Economic Zone (Assaluye), (Nov 2006 to Sep 2007)
- Installation of Heavy equipments , pumps , ducts , 896,000 kg
- Installation of all type of refractory material , 811,000 kg
- Fabrication and installation of metal Tanks , 94,000 kg
|
RAMSHIR C.T.C.
Back to Top
Installation of electrical and instrument of 10Th Olefins ( Main Unit of Jam Petrochemical ) In South Pars Special Economic Zone (Asaluye), (April 2004 to January 2005.)
Electrical works:
- Installation of 126 Cell Panel (MV , LV , UPS , Capacitor Bank , NGR , Wall mounted)
- Installation of 6 set busduct LV.
- Fabrication and installation of 28 ton Support, 23,500 Meter ladder, 1800 meter conduit.
- Installation of 13 Km lighting cables.
- Installation of 439 Nos. Explosion proof lighting fixtures and 515 Nos. Lighting junction boxes.
Instrument works:
- Fabrication and installation of 10 ton Support, 2300 Meter tray.
|
UNIGULF Co.
Back to Top
Erection, testing and commissioning
of cathodic protection of Pipeline for C2 Recovery (Assaluye), (2003 to 2004)
|
SEPAH MARINE CORPS
Back to Top
EPC (Engineering, procurement and construction of buildings, tanks, piping and other works of sepah marine corps station / JASK), (1997- 1999)
Civil works:
- Construction of concrete tank (for water storage) , Vol = 6000 m3
- Construction of concrete tank (for daily water storage) , Vol = 400 m3
- Construction of Pump station
- Construction of 6 Nos. Substation buildings.
- Construction of telecommunication room.
Mechanical works:
- Installation of 4000 meter Pipes for water network.
- Installation of 1600 meter Pipes for plumbing network.
- Installation of hydrants and fire fighting network.
- Installation of pumps at pump station.
Electrical works:
- Installation of panels (6 substation building and stores )
- Installation of building lighting (6 substation building and stores )
- Installation of 20 KV cables for main power of station.
- Installation of 12000 meter LV and lighting power cables for electrical power
and area lighting network.
- Installation of telecommunication panels and cables in telecom room.
And other electrical works.
|
TABRIZ PETROCHEMICAL COMPLEX
Back to Top
With NAVROOD Co. Joint Venture
(Erection, test and commissioning of substations and main laboratory), (1995- 1996)
Installation of all electrical devices for 4 set 20 KV Substation included:
- 10 Set transformers (2 , 4.2 , 7.5 MVA)
- 22 Cell MV panels.
- 43 Cell LV panels.
- 32 Cell Control panels. (Connection to ITR)
Installation of all electrical system for main Substations(1,2,3 & 4) , UTILITY buildings , Central Laboratory and N.D.T Laboratory included:
- Installation of building lighting system.
- Installation of building fire alarm system.
- Installation of earthing system.
- Installation of telecommunication system.
- Installation of cathodic protection system.
Installation of all instrument devices for Central Laboratory included:
- Installation of LAB devices.
- Installation of all tubes.
Installation of all mechanical system for Central Laboratory included:
- Installation of U/G piping.
- Installation of A/G piping.
- Installation of plumbing piping.
- Installation of 8000 meter pipes for production (for Central Laboratory)
Installation of all mechanical system for Other Building and Central Laboratory included:
- Installation of fire fighting piping and hydrants.
- Installation of CO2 piping and devices.
|
SHAHID TAHERI STORE (N.I.G.C)
Back to Top
EPC (Engineering, procurement and construction of All electrical work / SAVEH ), (1994- 1995), 16 Months
Electrical works:
- Installation of 24 Cell 20 KV Panels
- Installation of 44 Cell LV Panels
- Installation of 64 Cell lighting Panels
- Installation of 20 Cell Fire alarm Panels
- Installation of 60 set HV termination and 60,000 Nos. wire show and cable show.
- Installation of 430 Nos. Street Lighting poles
- Installation of 610 Nos. Luminaries for street lighting poles.
- Installation of 30,000 meter Cable ladder and tray
- Installation of 600,000 meter power cables.
- Installation of 10,000 meter control cables.
- Installation of 40,000 meter communication cables.
- Installation of 53,000 meter conduit.
- Installation of 2600 Nos. Fluorescent 3*40 watt.
- Installation of 5300 Nos. HPS Industrial Luminaries 250 watt.
- Installation of 16 Cell wall mounted and 30 Cell HVAC panels.
- Installation of 60,000 meter wire and 400 Nos. JB for lighting system.
Civil works:
- Installation of 430 Nos. concrete foundation for lighting poles
- Installation of 40,000 meter sleeve and Road crossing with 7000 m3 concrete
- 43,000 m3 excavation, sand filling and installation of concrete tile for cable pulling
|
LORESTAN REFEIGERATION INDUSTRIES
Back to Top
Erecting, testing and commissioning of electrical and mechanical systems.
Electrical works:
- Installation of 12 set transformers (2500 KVA)
- Installation of 73 Cell 20 KV Panels
- Installation of 64 Cell LV Panels
- Installation of 5 set capacitor banks (750 KVAR)
- Fabrication and installation of 70,000 kg support for electrical cables.
- Installation of 120,000 meter MV,LV and Control cables and other works of normal and emergency networks, lighting, central telephone, fire alarm, paging.
Mechanical works:
- Installation of 40,000 meter Piping for U/G and A/G Networks.
- Installation of 4300 kg Pumps
- Installation of 127,000 kg Boiling oil and water tanks.
- Installation of 24,000 kg other tanks.
and other works of pump station and fire fighting networks.
|